Amanda Harris, Senior Commissioning Manager, Author at PC Construction https://pcconstruction.com/news/author/aharris/ Building Stronger, Together Wed, 11 Feb 2026 17:37:21 +0000 en-US hourly 1 https://wordpress.org/?v=6.8.1 https://pcconstruction.com/app/uploads/2022/06/cropped-Site-Icon_02-32x32.jpg Amanda Harris, Senior Commissioning Manager, Author at PC Construction https://pcconstruction.com/news/author/aharris/ 32 32 Final Completion Achieved for WSSC Bioenergy Project https://pcconstruction.com/news/final-completion-achieved-for-wssc-bio-energy-project/ Wed, 11 Feb 2026 15:51:18 +0000 https://pcconstruction.com/?p=13522 The commissioning and closeout phase for WSSC Water’s Piscataway WRRF Bioenergy Project has successfully concluded, with final completion achieved in time for the New Year. Looking back on this one-of-a-kind project, which kicked off design in 2018, it is hard to put into words the enormity of the accomplishment associated with successfully starting up and […]

The post Final Completion Achieved for WSSC Bioenergy Project appeared first on PC Construction.

]]>
The commissioning and closeout phase for WSSC Water’s Piscataway WRRF Bioenergy Project has successfully concluded, with final completion achieved in time for the New Year. Looking back on this one-of-a-kind project, which kicked off design in 2018, it is hard to put into words the enormity of the accomplishment associated with successfully starting up and turning over a project of this scale on time and under budget. Since words just can’t describe it, I’ll quantify this last phase in numbers, all since handoff from construction in May 2024.

9 – The Commissioning Plan went into development at the 65% design stage in 2018 and, once completed, had nine volumes that detailed our approach to functional testing, programming verification, seeding and biological acclimation, sampling strategy, operational demonstration testing, and performance and acceptance testing. The volumes totaled over 2,160 pages of planning and test forms that laid the foundation for our successful turnover strategy.

10 – The number of process areas that were in various stages of testing at the same time. The PC closeout team divided up the plant – from the highly complex combined heat and power area to the extremely temperamental biological processes – and were able to execute testing safely and methodically to hit schedule milestones.

109 – The number of training sessions provided to the owner. At an average hourly session, this means that we trained for 27 weeks!

125 – There were 125 final Operation and Maintenance (O&M) manuals approved, updated, printed, and turned over to WSSC Water. To get to the final manual, each had to be submitted and approved for a preliminary and pre-final version. This resulted in 375 submissions just for O&M manuals! And that is on top of the 1,364 submittals the project team managed for a project this size.

2,740 – Hard input/output points were individually checked. And this doesn’t even get close to the soft IO points managed over ethernet for this project.

1,124 – The number of pages of programming process descriptions the team used to go line-by-line with the integrator to verify that all automation was functional, safe, and reliable.

1,314 – Assets entered into WSSC Water’s asset management program. As part of the closeout process, the team entered specific attributes ranging from size to horsepower and materials of construction that WSSC Water will use to identify, manage, and maintain the new infrastructure associated with this project.

34 – The longest continuous shift the commissioning team pulled to execute a series of tests. The team dedicated to the closeout of this project was amazing – they were committed to its success and were relentless in the pursuit of achieving performance and customer satisfaction.

306,782 – The number of samples and data points entered and analyzed during ramp-up and acclimation. From seeding through acceptance, a spreadsheet was maintained between WSSC Water and PC Construction to share sample results and real-time data so we could collaboratively make process decisions.

14 – There were 14 separate operational demonstration tests completed to prove the reliability of the facility, ranging from eight hours to continuous 30-day, 24/7 runs.

25 – There were 25 performance guarantee tests completed to prove the successful performance of the facility. These tests were designed to push systems and subsystems to their limits to ensure the system remains fully functional even in the most stringent conditions.

4 – The number of acceptance tests completed to achieve full acceptance of the facility.

The enormity of the commissioning process is so impressive to look back on. I am so proud and honored to have been a part of such a landmark project for WSSC. This project proved that with the right amount of collaboration and planning, anything is possible!

The post Final Completion Achieved for WSSC Bioenergy Project appeared first on PC Construction.

]]>
Potomac Raw Water Pump Station Completes Final Function Demonstration Test https://pcconstruction.com/news/potomac-raw-water-pump-station-completes-final-function-demonstration-test/ Wed, 16 May 2018 12:29:09 +0000 https://www.pcconstruction.com/blog/?p=5864 Loudoun Water’s new Potomac Raw Water Pumping Station is in the final stages of start-up and commissioning and is nearing site acceptance testing. The pump station will deliver up to 40 mgd of flow to the new Trap Rock Water Treatment Plant, which is also nearing the final stages of construction, for final treatment. The […]

The post Potomac Raw Water Pump Station Completes Final Function Demonstration Test appeared first on PC Construction.

]]>
Loudoun Water’s new Potomac Raw Water Pumping Station is in the final stages of start-up and commissioning and is nearing site acceptance testing. The pump station will deliver up to 40 mgd of flow to the new Trap Rock Water Treatment Plant, which is also nearing the final stages of construction, for final treatment. The flow is conveyed using a combination of four, 900-horsepower vertical turbine pumps with a pumping capacity of 9260 GPM each and 108-foot-deep shafts fed by 52-inch header piping that draws from the Potomac River.

Last week, the PC Construction teams filled the 42-inch diameter pipeline that connects the pump station and treatment plant over a six-mile distance in preparation for the pump station’s final functional demonstration test. The test confirmed the programming flow control pacing of the vertical turbine pumps over a range of 4 to 40 mgd.

The post Potomac Raw Water Pump Station Completes Final Function Demonstration Test appeared first on PC Construction.

]]>
Commissioning Pull Planning Session Results in Ownership and Accountability https://pcconstruction.com/news/commissioning-pull-planning-session-results-in-ownership-and-accountability/ Mon, 01 Aug 2016 14:26:11 +0000 https://www.pcconstruction.com/blog/?p=5209 The Commissioning Team at the DC Water Tunnel Dewatering Pump Station and Enhanced Clarification Facility recently conducted its first Pull Planning session. Pull Planning, which is a component of the Lean-based Last Planner System, helps develop a coordinated plan for a project component with influence from all people responsible for the associated work. The commissioning-based […]

The post Commissioning Pull Planning Session Results in Ownership and Accountability appeared first on PC Construction.

]]>
The Commissioning Team at the DC Water Tunnel Dewatering Pump Station and Enhanced Clarification Facility recently conducted its first Pull Planning session. Pull Planning, which is a component of the Lean-based Last Planner System, helps develop a coordinated plan for a project component with influence from all people responsible for the associated work.

The commissioning-based “pull” focused on the milestone of Operational Demonstration testing associated with the project’s consent decree date. The 18-month pull had a heavy focus on electrical, mechanical, and instrumentation and controls coordination as well as the document control associated with start-up and commissioning. Representatives from the subcontractors associated with the respective work joined the project team to ensure all key input was considered into the process.

The session was full of “ah-ha” moments. Everyone knew their role in getting to the finish line, but pull planning really emphasized how each individual role affected other trades. Key coordination issues and major equipment releases were brought to light and the team became aware of the need for field direction about power distribution priorities.

The pull was shared with our client, DC Water, and has been crucial in engaging them in the work. We’ve been able to identify a handful of high priority items that needed quick attention and set up workshops with DC Water to facilitate reviews and provide resources for removing potential obstacles. With all key team members involved, high priority submittal reviews and RFI responses have been handled efficiently.

The Last Planner System is a great way to get the entire team engaged, involved and fully in tune with project milestones. We are continuously utilizing the Pull Plan method to target milestones and work activities from our master 18-month Pull. It is amazing how the entire team is taking ownership of their roles and being accountable to one another through this process.

The post Commissioning Pull Planning Session Results in Ownership and Accountability appeared first on PC Construction.

]]>